Honeygo Elementary School
Total Sitework Package
Baltimore County Public Schools
Perry Hall, MD
Honeygo Elementary was a net new construction project with a project budget of $49M. The school was constructed to relieve overcrowding of neighboring schools.
12.87 acres of disturbed area including:
- Clearing and demolition
- Mass grading
- Stormwater Management and Bioretention Facilities
- Utilities and utility demolition
- Turfgrass and Landscaping
- Ground loop piping – Geothermal System
- Site concrete
- Fencing
- Asphalt Paving
- Striping and Signage
- Stream Restoration & Box Culvert
- Pedestrian Bridge